Question 13 - PgMP discussion
You are the program manager for the SRQ Program. You have rejected several change requests for the program scope. What must you do with the rejected change requests?
A.
Communicate why the change request was rejected and record the results in the lessons learned documentation for your program.
B.
Inform the stakeholders that their change requests have been rejected.
C.
Communicate the change request status to the stakeholders and record the results of the change request in the change register.
D.
Inform the stakeholders why their change requests have been rejected.