You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?

A.
Contract administration
Answers
A.
Contract administration
B.
Resource management
Answers
B.
Resource management
C.
Resource control
Answers
C.
Resource control
D.
Procurement management
Answers
D.
Procurement management
Suggested answer: C