A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?

A.
Program risk
Answers
A.
Program risk
B.
Program benefits
Answers
B.
Program benefits
C.
Program scope
Answers
C.
Program scope
D.
Link to organizational strategy
Answers
D.
Link to organizational strategy
Suggested answer: A