A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?

A.
$978,445
Answers
A.
$978,445
B.
$919,325
Answers
B.
$919,325
C.
$991,667
Answers
C.
$991,667
D.
$987,544
Answers
D.
$987,544
Suggested answer: C