When a change enters your program requirements you must update all of the following documents except for which one?

A.
Program work breakdown structure
Answers
A.
Program work breakdown structure
B.
Program activity list
Answers
B.
Program activity list
C.
Program charter
Answers
C.
Program charter
D.
Program scope
Answers
D.
Program scope
Suggested answer: C