You are the program manager for your organization and you are preparing to launch several constituent projects within your program. You need to ensure that each project manager is authorized to utilize the appropriate project and program resources in order to complete the project requirements. What document do you need to create for each constituent project in your program to ensure that each project manager can use the appropriate resources?

A.
Project charter
Answers
A.
Project charter
B.
Project scope statement
Answers
B.
Project scope statement
C.
Project resource requirements document
Answers
C.
Project resource requirements document
D.
Roles and responsibilities chart
Answers
D.
Roles and responsibilities chart
Suggested answer: A