Robert is the program manager of the NHQ Program. His team has never worked with one another before this program and he is worried about their abilities to become a team in very short order. He would like to create a team development exercise to facilitate this process. Robert will need all of the following information except for which one to facilitate team development?

A.
Risk management plan
Answers
A.
Risk management plan
B.
Program management plan
Answers
B.
Program management plan
C.
Personnel records
Answers
C.
Personnel records
D.
Training records
Answers
D.
Training records
Suggested answer: A