You are the program manager for your organization. You're currently creating an accountability matrix starting with yourself, the program manager and the program sponsor. What program management process identifies the program sponsor?

A.
Pre-program setup phase
Answers
A.
Pre-program setup phase
B.
Authorization of program processes and projects
Answers
B.
Authorization of program processes and projects
C.
Initiate program process
Answers
C.
Initiate program process
D.
Initiation of the program management team
Answers
D.
Initiation of the program management team
Suggested answer: C