Question 98 - PgMP discussion
You are the program manager of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all of the project managers before. Even though you've worked with the project managers before you still need to define the authority of the project managers and their projects. What document names the project manager for the project?
A.
Project charter for each project
B.
Program human resource management plan
C.
Project scope statement
D.
Program management charter