A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?

A.
Reactionary risks
Answers
A.
Reactionary risks
B.
Chain risks
Answers
B.
Chain risks
C.
Secondary risks
Answers
C.
Secondary risks
D.
In flux risks
Answers
D.
In flux risks
Suggested answer: C