Question 103 - PgMP discussion

Report
Export

You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project to save time and effort. This is an example of what kind of scope definition?

A.
Analogous estimating
Answers
A.
Analogous estimating
B.
Organizational process assets
Answers
B.
Organizational process assets
C.
Parametric scope definition
Answers
C.
Parametric scope definition
D.
Template driven
Answers
D.
Template driven
Suggested answer: D