Question 108 - PgMP discussion

Report
Export

You are the program manager for your organization. Your program will create a new condominium in your community. There are several concerns about the condos including the timing, the local economy, the environment, and the proposed schedule. You and your team are creating the program management plan to address these concerns along with identifying the constituent projects that will build the structures and deliverables. What group will need to review your program plan to approve the plan before you may proceed in the work?

A.
The local government
Answers
A.
The local government
B.
The change control board
Answers
B.
The change control board
C.
The stakeholders
Answers
C.
The stakeholders
D.
The program board
Answers
D.
The program board
Suggested answer: D