Which project management meeting allows stakeholders to meet one another and to learn about the project?

A.
Project scope review
Answers
A.
Project scope review
B.
Project authorization meeting
Answers
B.
Project authorization meeting
C.
Project status meeting
Answers
C.
Project status meeting
D.
Project kick-off meeting
Answers
D.
Project kick-off meeting
Suggested answer: D