You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?
A.
Contract and the quality measurements for the vendor's work
B.
The scope verification document and the termination notice
C.
Contract and scope verification process documents
D.
Work that has been completed and uncompleted work