You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?

A.
Whenever the program needs to initiate projects, it may, as long as the program has not entered the closing processes of the program.
Answers
A.
Whenever the program needs to initiate projects, it may, as long as the program has not entered the closing processes of the program.
B.
With program execution
Answers
B.
With program execution
C.
With program initiation
Answers
C.
With program initiation
D.
With program planning
Answers
D.
With program planning
Suggested answer: A