Question 123 - PgMP discussion
You are the program manager for the HQM Program. Your program has sixteen constituent projects around the world. You are requiring that each project manager and project management team use the same forms, software, and templates to create standardization in each project. What term is assigned to the forms, templates, and software that your program will provide for your projects?
A.
Program governance
B.
Project management assets
C.
Enterprise environmental factors
D.
Organizational process assets