Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?
A.
Resource breakdown structure
B.
Resource management chart
C.
Stakeholder analysis chart
D.
RACI chart