Question 126 - PgMP discussion

Report
Export

Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?

A.
Resource breakdown structure
Answers
A.
Resource breakdown structure
B.
Resource management chart
Answers
B.
Resource management chart
C.
Stakeholder analysis chart
Answers
C.
Stakeholder analysis chart
D.
RACI chart
Answers
D.
RACI chart
Suggested answer: C