Question 129 - PgMP discussion

Report
Export

You are the program manager for your organization and you're coaching Tom, an aspiring program manager, on program management. Tom is curious about controlling communications. Which one of the following is an output of the communications control process?

A.
Approved change requests
Answers
A.
Approved change requests
B.
Communications management plan
Answers
B.
Communications management plan
C.
Stakeholder analysis charts
Answers
C.
Stakeholder analysis charts
D.
Performance reports
Answers
D.
Performance reports
Suggested answer: B