You are the program manager for the HNY Corporation and you complete programs for other companies in your role. You have just been assigned a new program that is very similar to a recently completed program you did for your company. Management has asked you to create a cost estimate for the program so you base your current cost estimate on the recently finished program. What type of estimating technique have you used in this instance?

A.
Bottom-up
Answers
A.
Bottom-up
B.
Parametric
Answers
B.
Parametric
C.
Analogous
Answers
C.
Analogous
D.
Rough order of magnitude
Answers
D.
Rough order of magnitude
Suggested answer: C