You are the program manager for your organization and working to create the program statement of work for approval by the program director. All of the following information is defined in the program statement of work except for which one?

A.
Program requirements for resource competency levels
Answers
A.
Program requirements for resource competency levels
B.
Structure of the program management team
Answers
B.
Structure of the program management team
C.
Metrics and qualifications for program acceptance
Answers
C.
Metrics and qualifications for program acceptance
D.
Location of the program work
Answers
D.
Location of the program work
Suggested answer: B