Tom is the program manager for his organization. He has to balance the resources he'll be using in the program with the demand for operations to use the same resources. What program document can Tom reference to determine the availability of certain program resources, such as application developers, engineers, and technical writers?

A.
Staffing management plan
Answers
A.
Staffing management plan
B.
Resource calendar
Answers
B.
Resource calendar
C.
Functional management plan
Answers
C.
Functional management plan
D.
The resource pool description
Answers
D.
The resource pool description
Suggested answer: B