An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts, the program manager discovers the program may be shut down due to lack of funding.

To ensure continued funding for the program, what should the program manager do next?

A.
Complete the benefits sustainment plan and update the benefits register
Answers
A.
Complete the benefits sustainment plan and update the benefits register
B.
Present a revised ROI to the program sponsors based on the remaining investment
Answers
B.
Present a revised ROI to the program sponsors based on the remaining investment
C.
Conduct a cost-benefit analysis to ensure the program sponsors understand the program's long-term benefits
Answers
C.
Conduct a cost-benefit analysis to ensure the program sponsors understand the program's long-term benefits
D.
Review the program business case and the program's strategic alignment and long-term benefits with the program governance board
Answers
D.
Review the program business case and the program's strategic alignment and long-term benefits with the program governance board
Suggested answer: C