A program manager prepares the program for review to secure funding by senior management. Which of the following must the program manager identify when creating the program charter?
A.
Milestone dates, budget, and staff details that support it
B.
Assumptions incorporated into the benefits management plan
C.
Process within the organization that will be needed to deliver the product
D.
Key decision makers or stakeholders in the program and their expectations and interests