Question 348 - PgMP discussion
A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change.
To whom should the change request be presented?
A.
The program governance board
B.
The program customer
C.
The program management office (PMO)
D.
The project governance board