Question 348 - PgMP discussion

Report
Export

A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change.

To whom should the change request be presented?

A.
The program governance board
Answers
A.
The program governance board
B.
The program customer
Answers
B.
The program customer
C.
The program management office (PMO)
Answers
C.
The program management office (PMO)
D.
The project governance board
Answers
D.
The project governance board
Suggested answer: A