A company wants to perform a preliminary stakeholder analysis to assess a new program's support.

What should the program manager develop?

A.
Program communications management plan and the stakeholder charter
Answers
A.
Program communications management plan and the stakeholder charter
B.
Responsible, accountable, consult, and inform (RACI) matrix, stakeholder list, and escalation process
Answers
B.
Responsible, accountable, consult, and inform (RACI) matrix, stakeholder list, and escalation process
C.
Stakeholder strengths, weaknesses, opportunities and threats (SWOT) analysis
Answers
C.
Stakeholder strengths, weaknesses, opportunities and threats (SWOT) analysis
D.
Stakeholder engagement plan, stakeholder register, and stakeholder map
Answers
D.
Stakeholder engagement plan, stakeholder register, and stakeholder map
Suggested answer: D