Question 362 - PgMP discussion

Report
Export

A program sponsor is concerned about the status of high-priority risks and budget variances.

The program manager should refer to which of the following?

A.
Program status dashboard
Answers
A.
Program status dashboard
B.
Program management plan
Answers
B.
Program management plan
C.
Program performance report
Answers
C.
Program performance report
D.
Program management information system (PMIS)
Answers
D.
Program management information system (PMIS)
Suggested answer: A