Question 362 - PgMP discussion
A program sponsor is concerned about the status of high-priority risks and budget variances.
The program manager should refer to which of the following?
A.
Program status dashboard
B.
Program management plan
C.
Program performance report
D.
Program management information system (PMIS)
Your answer: