A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase. Tracking and reporting of actual benefits realized is one part of the review.
What is the other part of the review?
A.
Tracking and reporting on benefits management plan
B.
Identifying factors influencing delivery of benefits
C.
Demonstrating that other stage gate requirements have been met
D.
Gathering additional stakeholders' requirements