What would prevent a program manager from completing program closure once a program has been completed?

A.
Failure to update the financial management plan
Answers
A.
Failure to update the financial management plan
B.
Failure to update the benefits register
Answers
B.
Failure to update the benefits register
C.
Incomplete realization of all program benefits
Answers
C.
Incomplete realization of all program benefits
D.
Failure to obtain program steering committee approval
Answers
D.
Failure to obtain program steering committee approval
Suggested answer: B