Question 388 - PgMP discussion
In the last year, all program phase gate reviews received excellent feedback and exceeded stakeholder expectations. Recently, the customer decides that there is no need to continue phase gate reviews.
What should the program manager do next?
A.
Ask the stakeholders what they want and proceed with their recommendations.
B.
Agree with the customer and initiate change control procedures.
C.
Continue periodic gate reviews to maintain program effectiveness for benefits realization.
D.
Replace program reviews with periodic communications of the program's status.
Your answer: