A program has been established and preparation is complete.

Component projects are planned as a part of which of the following?

A.
Program definition phase
Answers
A.
Program definition phase
B.
Program formulation
Answers
B.
Program formulation
C.
Program planning
Answers
C.
Program planning
D.
Program delivery phase
Answers
D.
Program delivery phase
Suggested answer: B