Question 412 - PgMP discussion
A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.
What should the program manager do next to address this risk?
A.
Prioritize which resources are critical to the project based on an impact analysis of the critical change requests and update the program roadmap.
B.
Prioritize which change requests are critical to the project based on an impact analysis, resource only critical change requests until overdue milestones are achieved, and update the risk register.
C.
Mandate that no component project change requests will be processed until overdue milestones have been completed and update the risk register to reflect this.
D.
Add the lack of skilled resources to facilitate the large number of change requests to the issue log.