Question 419 - PgMP discussion

Report
Export

The program manager has a global program with five component projects. The program sponsor wants the management plans, processes/procedures, and technology to be uniform across the program. The requirements will create issues and result in increased costs The program sponsor is new and has imposed these new requirements six months into a three-year program.

What should the program manager do next?

A.
Accept what the program sponsor requires and implement the changes.
Answers
A.
Accept what the program sponsor requires and implement the changes.
B.
Discuss the proposed changes with the stakeholders and project managers, and give the program sponsor the best option.
Answers
B.
Discuss the proposed changes with the stakeholders and project managers, and give the program sponsor the best option.
C.
Respond to the program sponsor if the program sponsor asks about it a second time.
Answers
C.
Respond to the program sponsor if the program sponsor asks about it a second time.
D.
Present the risks and benefits of the changes to the program sponsor.
Answers
D.
Present the risks and benefits of the changes to the program sponsor.
Suggested answer: B, C