Question 421 - PgMP discussion
A program delivers incremental benefits, but is far from closure. The company completes an acquisition and defines new strategic objectives.
What should the program manager do next?
A.
Evaluate the impact of the new strategic objectives through a change request.
B.
Integrate the new acquisition into the program to include the new strategic objectives.
C.
Assess the impact of the new acquisition on the contract management plan.
D.
Review the benefits management plan to assess the continued validity of the program.