A company CEO issues a mandate to automate a new-client onboarding process to replace manual and paper-based procedures. After the program sponsor and program manager obtain formal acceptance of the program charter, what should be done next?
A.
Deploy a team to develop the program management plan.
B.
Develop estimates for scope, resources, and cost.
C.
Identify the program management components, and develop the resource management plan.
D.
Review and update the benefits management plan and link it to program outcomes.