A program manager initiates a new global program to create a higher level of protection for a company's intellectual property. The company exhibits a relaxed culture and environment, and is intolerant of processes to the point of being considered process-adverse. However, the company's culture is tolerant of long-term program activities, provided there is continuous progress on improving the protection of its intellectual property. Expectations for rapid progress are low.

What should the program manager do next?

A.
Tailor program sponsor and stakeholder engagement and communications activities to meet the company's expectations
Answers
A.
Tailor program sponsor and stakeholder engagement and communications activities to meet the company's expectations
B.
Insist on maintaining a set of tightly controlled stakeholder register and engagement plan documents to meet expectations
Answers
B.
Insist on maintaining a set of tightly controlled stakeholder register and engagement plan documents to meet expectations
C.
Provide detailed information to the most influential program sponsors and stakeholders
Answers
C.
Provide detailed information to the most influential program sponsors and stakeholders
D.
Ensure that the component stakeholders have the appropriate level of communications required to meet their needs
Answers
D.
Ensure that the component stakeholders have the appropriate level of communications required to meet their needs
Suggested answer: B