Question 432 - PgMP discussion

Report
Export

A new component project is approved by the program governance board. The funding for this component project will be provided by an organization different from the organization funding the program.

Would this be an acceptable funding arrangement?

A.
Yes, only component projects may have different funding sources.
Answers
A.
Yes, only component projects may have different funding sources.
B.
Yes, the program and its components may have different funding sources.
Answers
B.
Yes, the program and its components may have different funding sources.
C.
No, the program and the project must be funded by the same organization.
Answers
C.
No, the program and the project must be funded by the same organization.
D.
No, component projects must be funded by program funds.
Answers
D.
No, component projects must be funded by program funds.
Suggested answer: A