List of questions
Related questions
Question 435 - PgMP discussion
A large infrastructure development program involves three road construction projects, two sewage line construction projects, and one project to lay underground electric cables. During a program meeting, the project manager of a road construction project communicates that a project risk related to the interdependency with a sewage line project has crossed its risk threshold.
What should the program manager do next?
A.
Modify the program schedule to accommodate the risk.
B.
Incorporate the project risk into the program risk response strategy.
C.
Instruct the project manager to escalate the risk to the program sponsor.
D.
Ask the road construction project manager to manage the risk at the project level.
Your answer:
0 comments
Sorted by
Leave a comment first