After attending a technology exposition, an influential stakeholder believes that integrating a new technology into the program will increase benefits and help shorten the schedule. The stakeholder asks the program manager to immediately include the new technology into the program.

What should the program manager do next?

A.
Assess the new technology and discuss the results with the program steering committee to determine next steps.
Answers
A.
Assess the new technology and discuss the results with the program steering committee to determine next steps.
B.
Start the change management process and submit a change request to integrate the new technology.
Answers
B.
Start the change management process and submit a change request to integrate the new technology.
C.
Inform the stakeholder that the program will not be changed until proof of concept (PoC) is completed.
Answers
C.
Inform the stakeholder that the program will not be changed until proof of concept (PoC) is completed.
D.
Research the new technology and begin its integration during the next development cycle.
Answers
D.
Research the new technology and begin its integration during the next development cycle.
Suggested answer: C