What term is used to describe boards that display what work needs to be completed for people working on a project?

Work in progress limit
Work in progress limit
Information radiator
Information radiator
Highlight report
Highlight report
Glad! Sad! Mad!
Glad! Sad! Mad!
Suggested answer: C

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_190&showNav=true&expandNav=true

asked 23/09/2024
femke vroome
47 questions

Question 12

Report
Export
Collapse

Which two statements about tailoring the business case in an agile environment are CORRECT?

It should be unnecessary because products of the highest value will be delivered first.
It should be unnecessary because products of the highest value will be delivered first.
It should identify the minimum viable product and when it will be delivered.
It should identify the minimum viable product and when it will be delivered.
It should take into account that the scope may be reduced during the course of the project.
It should take into account that the scope may be reduced during the course of the project.
It should show the features, the order in which they will be delivered and any dependencies.
It should show the features, the order in which they will be delivered and any dependencies.
1 and 2
1 and 2
2 and 3
2 and 3
3 and 4
3 and 4
1 and 4
1 and 4
Suggested answer: B
asked 23/09/2024
Simon Merlin AGHOKENG
39 questions

Question 13

Report
Export
Collapse

What should the business case state about the minimum viable product (MVP)?

When the MVP will be defined
When the MVP will be defined
That the MVP must go into operational use
That the MVP must go into operational use
What the MVP is
What the MVP is
That the MVP is the same as project viability
That the MVP is the same as project viability
Suggested answer: B

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_56&showNav=true&expandNav=true

asked 23/09/2024
Vojtech Danek
38 questions

Question 14

Report
Export
Collapse

How does the change theme regard change in PRINCE2 Agile?

As disruptive
As disruptive
As something to be avoided
As something to be avoided
As a necessity
As a necessity
As inevitable
As inevitable
Suggested answer: D

Explanation:

Reference: https://edward-designer.com/web/prince2-foundation-notes-change-theme/

asked 23/09/2024
patricia rosales
34 questions

Question 15

Report
Export
Collapse

Which statement about the ‘keep teams stable’ target is CORRECT?

It applies primarily to the long term, such as a project or a program
It applies primarily to the long term, such as a project or a program
It is the primary reason why the tolerance for cost is set to zero
It is the primary reason why the tolerance for cost is set to zero
It prevents compromising the overall quality level of the product
It prevents compromising the overall quality level of the product
It results in the early delivery of a minimum viable product
It results in the early delivery of a minimum viable product
Suggested answer: B

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_41

asked 23/09/2024
Vincent Chung
35 questions

Question 16

Report
Export
Collapse

What needs to happen when new detailed requirements are added to a timebox?

Requirements of a similar level of effort should be removed
Requirements of a similar level of effort should be removed
More people should be added to the delivery team
More people should be added to the delivery team
The delivery milestones should be reviewed and re-planned
The delivery milestones should be reviewed and re-planned
Formal change control should be applied
Formal change control should be applied
Suggested answer: A
asked 23/09/2024
Zarate, Wilfredo
41 questions

Question 17

Report
Export
Collapse

Which statement about the ‘accept that the customer doesn’t need everything’ target is correct?

It gives confidence on the progress of the project
It gives confidence on the progress of the project
It can result in the early delivery of a minimum viable product
It can result in the early delivery of a minimum viable product
It allows misunderstandings to be dealt with appropriately
It allows misunderstandings to be dealt with appropriately
It is achieved by managing the culture of the team carefully
It is achieved by managing the culture of the team carefully
Suggested answer: C
asked 23/09/2024
antoine sala
35 questions

Question 18

Report
Export
Collapse

Which statement about velocity is CORRECT?

It is based on the concept of rationalism
It is based on the concept of rationalism
It is shown by the ideal line on a bum-down chart
It is shown by the ideal line on a bum-down chart
It describes how much work is getting done
It describes how much work is getting done
It tracks the time and cost of a timebox
It tracks the time and cost of a timebox
Suggested answer: C

Explanation:

Reference: https://worldofagile.com/blog/velocity/

asked 23/09/2024
Vinayak H
35 questions

Question 19

Report
Export
Collapse

Which is a purpose of the ‘controlling stage’ process?

To execute and deliver the project product
To execute and deliver the project product
To establish whether the project is complete
To establish whether the project is complete
To report stage progress to the project board
To report stage progress to the project board
To draft the plan for the next stage’s work
To draft the plan for the next stage’s work
Suggested answer: C

Explanation:

Reference:

https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_117&showNav=true&expandNav=true#:~:text=The%20purpose%20of%20the%20Controlling,the%20stage%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control

asked 23/09/2024
Tanya Resto
40 questions

Question 20

Report
Export
Collapse

Which is a typical characteristic of ‘business as usual’ work?

It requires a specific dedicated project manager
It requires a specific dedicated project manager
It is executed by program management
It is executed by program management
It is delivered by a temporary team
It is delivered by a temporary team
It is delivered by an established team
It is delivered by an established team
Suggested answer: D

Explanation:

Reference: https://www.prince2primer.com/prince2-agile-overview-part-1/