Question 32 - PRINCE2 Agile Foundation discussion

Report
Export

What is the definition of a timebox?

A.
A tool to write a requirement in the form of who, what and why
Answers
A.
A tool to write a requirement in the form of who, what and why
B.
A regular event that looks at how processes can be improved
Answers
B.
A regular event that looks at how processes can be improved
C.
A description of the rate of progress a team is making
Answers
C.
A description of the rate of progress a team is making
D.
A period where work is carried out to achieve a goal
Answers
D.
A period where work is carried out to achieve a goal
Suggested answer: D

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_244