Which statement explains the PRINCE2 Agile behavior of ‘exploration’?

A.
It empowers the project management team at the delivery level
Answers
A.
It empowers the project management team at the delivery level
B.
It uses the most effective channel to communicate information
Answers
B.
It uses the most effective channel to communicate information
C.
It displays the progress rate to everyone using burn-down charts
Answers
C.
It displays the progress rate to everyone using burn-down charts
D.
It seeks out feedback collaboratively from project stakeholders
Answers
D.
It seeks out feedback collaboratively from project stakeholders
Suggested answer: D

Explanation:

Reference:

https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_47&showNav=true&expandNav=true

asked 23/09/2024
Wallace Davison
35 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first