Question 58 - PRINCE2 Agile Foundation discussion

Report
Export

Which should be an objective of a retrospective?

A.
To identify many process improvements and implement them
Answers
A.
To identify many process improvements and implement them
B.
To identify key process improvements to implement in the next sprint
Answers
B.
To identify key process improvements to implement in the next sprint
C.
To encourage the team to bond by allowing social activities to take place
Answers
C.
To encourage the team to bond by allowing social activities to take place
D.
To focus on objective learning rather than subjective feelings and emotions
Answers
D.
To focus on objective learning rather than subjective feelings and emotions
Suggested answer: B