Universal Containers uses Kanban to complete its Salesforce development. In the middle of a sprint, the sales manager submits an important item to the team.
What should the business analyst do next?
A.
Ask the team to reprioritize the backlog and work on the item at the top.
B.
Ask the team to commit to the work for the next sprint.
C.
Ask the team to pivot and complete the work immediately.