Question 14 - PSPO-I discussion
The IT manager asks a Scrum Team for a status report describing the progress throughout the Sprint. The Scrum Team asks the Scrum Master for advice. The Scrum Master should:
(choose the best answer)
A.
Tell the Developers to fit the report into the Sprint Backlog.
B.
Ask the Product Owner to send the manager the report.
C.
Create and deliver the report to the manager herself.
D.
Tell the Scrum Team to figure it out themselves.
E.
Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.