ExamGecko
Question list
Search
Search

Question 14 - PSPO-I discussion

Report
Export

The IT manager asks a Scrum Team for a status report describing the progress throughout the Sprint. The Scrum Team asks the Scrum Master for advice. The Scrum Master should:

(choose the best answer)

A.
Tell the Developers to fit the report into the Sprint Backlog.
Answers
A.
Tell the Developers to fit the report into the Sprint Backlog.
B.
Ask the Product Owner to send the manager the report.
Answers
B.
Ask the Product Owner to send the manager the report.
C.
Create and deliver the report to the manager herself.
Answers
C.
Create and deliver the report to the manager herself.
D.
Tell the Scrum Team to figure it out themselves.
Answers
D.
Tell the Scrum Team to figure it out themselves.
E.
Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.
Answers
E.
Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.
Suggested answer: E

Explanation:

The Scrum Master should talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review. This is because:

The Scrum Team is self-managing and does not need to report to anyone outside the team1.

The Sprint Review is an event where the Scrum Team and the stakeholders collaborate on the product and inspect the Increment2.

The Increment is a concrete and usable outcome of the Sprint that provides a measure of progress and value delivery3.

The IT manager can attend the Sprint Review as a stakeholder and provide feedback on the product and the process4.

Scrum Guide, page 7, section "The Scrum Team"

Scrum Guide, page 13, section "Sprint Review"

Scrum Guide, page 10, section "Increment"

Scrum Guide, page 14, section "Sprint Review"

asked 23/09/2024
Alejandro Yepez
47 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first