Question 23 - PSPO-I discussion
When does a Developer become accountable for the value of a Product Backlog item selected for the Sprint?
(choose the best answer)
A.
Whenever a team member can accommodate more work.
B.
At the Sprint Planning Event.
C.
During the Daily Scrum.
D.
Never. The entire Scrum Team is accountable for creating value every Sprint.