Which of these may a Scrum Team deliver at the end of a Sprint?
(choose the best answer)
A.
Failing unit tests, to identify acceptance tests for the next Sprint.
B.
A single document, if that is what management asked for.
C.
An Increment of software with minor known bugs in it.
D.
A valuable, useful Increment that meets the Definition of Done.