Which of these may a Scrum Team deliver at the end of a Sprint?

(choose the best answer)

A.
Failing unit tests, to identify acceptance tests for the next Sprint.
Answers
A.
Failing unit tests, to identify acceptance tests for the next Sprint.
B.
A single document, if that is what management asked for.
Answers
B.
A single document, if that is what management asked for.
C.
An Increment of software with minor known bugs in it.
Answers
C.
An Increment of software with minor known bugs in it.
D.
A valuable, useful Increment that meets the Definition of Done.
Answers
D.
A valuable, useful Increment that meets the Definition of Done.
Suggested answer: D

Explanation:

The Scrum Guide states that "the Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints". It also states that "at the end of a Sprint, the new Increment must be 'Done', which means it must be in useable condition and meet the Scrum Team's definition of 'Done"'. Therefore, the Scrum Team must deliver a valuable, useful Increment that meets the Definition of Done at the end of a Sprint. The other options are not acceptable, as they do not meet the criteria of being valuable, useful, or done.

The Scrum Guide, section 3.4. Increment

Professional Scrum Product Owner I (PSPO I) Learning Path, section 2.1. The Product Owner and the Development Team