ExamGecko
Question list
Search
Search

Question 164 - PSPO-I discussion

Report
Export

How much time is required after a Sprint to prepare for the next Sprint?

(choose the best answer)

A.
The break between Sprints is timeboxed to one-week for a one-month Sprint, and usually less for shorter Sprints.
Answers
A.
The break between Sprints is timeboxed to one-week for a one-month Sprint, and usually less for shorter Sprints.
B.
Enough time for the requirements for the next Sprint to be determined and documented.
Answers
B.
Enough time for the requirements for the next Sprint to be determined and documented.
C.
Enough time for the Developers to finish the testing from the last Sprint.
Answers
C.
Enough time for the Developers to finish the testing from the last Sprint.
D.
None. A new Sprint starts immediately following the end of the previous Sprint.
Answers
D.
None. A new Sprint starts immediately following the end of the previous Sprint.
E.
All of the above are allowed depending on the situation.
Answers
E.
All of the above are allowed depending on the situation.
Suggested answer: D

Explanation:

The Scrum Guide states that 'Sprints have consistent durations throughout a development effort.A new Sprint starts immediately after the conclusion of the previous Sprint.'1This means that there is no gap or break between Sprints, and the Scrum Team does not need to spend extra time to prepare for the next Sprint. The Scrum Team should be able to start the next Sprint Planning right after the Sprint Review and Sprint Retrospective of the previous Sprint. The Scrum Team should also ensure that the testing and documentation of the work are done within the Sprint, and not left for later.

1: The Scrum Guide2, page 9

2:The Scrum Guide

asked 23/09/2024
Muhammad Imran Khan
35 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first