Scrum PSPO-I Practice Test - Questions Answers, Page 17
List of questions
Question 161
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
What is the accountability of the Product Owner during Sprint 0?
(choose the best answer)
Question 162
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days?
(choose the best three answers)
Question 163
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which approach is best for Scrum Teams in order to produce valuable Increments?
(choose the best answer)
Question 164
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
How much time is required after a Sprint to prepare for the next Sprint?
(choose the best answer)
Question 165
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
During the Sprint Retrospective a Scrum Team has identified several high priority process improvements. Which of the following statements is most accurate?
(choose the best answer)
Question 166
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
What does it mean to say that an event has a timebox?
(choose the best answer)
Question 167
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
What is a Product Owner typically responsible for during a Sprint?
(choose the best two answers)
Question 168
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which of the following is an example of an Increment?
(choose the best answer)
Question 169
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A product's success is measured by:
(choose the best three answers)
Question 170
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
What is the typical size for a Scrum Team?
(choose the best answer)
Question