Question 4 - PSPO-II discussion
Which of the following statements about the Product Backlog are true?
(choose the best two answers)
A.
The Product Backlog is ordered by the Product Owner.
B.
The Product Backlog should be visible to the Scrum Team and stakeholders.
C.
All Product Backlog items must be expressed as user stories.
D.
All Product Backlog items must be identified before the first Sprint begins.
E.
Only the Product Owner can place items on the Product Backlog.
F.
The Product Backlog represents the input of all stakeholders and eliminates any need for the Developers to speak to stakeholders.
Your answer: