Question 9 - PSPO-II discussion
The Developers inform the Product Owner during the Sprint that they are not likely to complete everything they forecasted. What would you expect a Product Owner to do?
(choose the best answer)
A.
Reduce the scope of the Sprint, if possible, to still meet the Sprint Goal.
B.
Skip Product Backlog refinement activities.
C.
End the Sprint, since the goal cannot be achieved.
D.
Change the Sprint Goal to match what the Developers can deliver.
E.
Inform management that more resources are needed.