List of questions
Question 20 - PSPO-II discussion
As a Product Owner you become aware that the quality assurance criteria, defined in the Definition of Done, were not met for the latest Increment. Which of the following statements are true?
(choose the best four answers)
A.
The next Sprint may be interrupted when quality issues are encountered.
B.
The project manager cannot effectively update the plan.
C.
The indication of progress on the Product Backlog is not transparent.
D.
The Scrum Team should not release the Increment.
E.
The incomplete Sprint Backlog items should be returned to the Product Backlog.
Your answer:
0 comments
Sorted by
Leave a comment first